This week, the Contractor completed sanitary, water and storm sewer lateral installation; and the final watermain connections. There are no more planned water service outages for the project. The contractor worked to install sidewalk, concrete terrace and planting curbs between Wells Street and Pierce Ave/Wisconsin Street.
Planned work for this week is as follows:
- Early week- storm sewer at the intersection of Pierce Ave and Wisconsin Street
- Middle of week- roadway excavation and new base course installation on Main
- Street between Pierce Ave/Wisconsin Street and Hall Ave
- End of Week- underground conduit installation for light poles between Pierce Ave/Wisconsin Street and Hall Ave