Construction continues this week along the Main Street project corridor in Marinette. Last week, crews poured new concrete sidewalk between Pierce and Hall avenues and prepped the raised speed table in the center of the project zone.
This week, work will include:
- More sidewalk installation
- Concrete paving in the speed table
- Work in the plaza area
- Pavement markings
- And general clean-up.
City officials say they’ll evaluate conditions Friday morning, October 31st, to determine whether the roadway can safely reopen to motorized traffic. Officials plan to release an update on Friday.
If you have questions about the project or would like to receive construction updates by email, you can contact the city for more information.